Kerala’s Tunnel Rail Connectivity Project: Unlocking Trade Access Across Southern India

Introduction

In a strategic move to bolster freight infrastructure and unlock the economic potential of southern India, the Government of Kerala is preparing to float a tender for the engineering, procurement and construction (EPC) of a tunnel rail connectivity project linking Vizhinjam International Seaport with Balaramapuram railway station. Estimated at ₹1,483 crore, the project is expected to transform Vizhinjam from a transhipment hub into a full-fledged cargo gateway, enhancing multimodal logistics and regional trade access.

A high-level meeting convened in Thiruvananthapuram brought together senior officials from the state government, Vizhinjam International Seaport Ltd (VISL), and Konkan Railway Corporation Ltd (KRCL). KRCL presented a detailed technical proposal, which reportedly received broad approval. However, VISL and government representatives proposed several modifications and raised counterpoints, prompting the scheduling of a final review meeting in early September to finalise the tender documentation.

Timelines and Milestones

  • Tender publication: Expected September 2025
  • Bid submission deadline: To be announced in the tender notice
  • Contract award: Anticipated by Q1 2026
  • Construction commencement: Scheduled for mid-2026
  • Project completion: Targeted by the end of 2028

Project Scope and Technical Highlights

The proposed alignment spans approximately 10.7 kilometres, with 9.4 kilometres running through a tunnel constructed using the New Austrian Tunnelling Method (NATM), a technique known for its adaptability to complex geological conditions and minimal surface disruption. The tunnel will reach depths of 25 to 30 metres below ground, and freight trains are expected to traverse the route in approximately 36 minutes, operating at speeds between 15 and 30 km/h.

The project will include:

  • NATM-based tunnel engineering with advanced safety and ventilation systems
  • Integration with the existing rail infrastructure at Balaramapuram
  • Environmental impact assessments and mitigation strategies
  • Digital monitoring systems for tunnel integrity and train movement

Strategic Importance

Vizhinjam port’s location along international shipping lanes positions it as a critical node in India’s maritime logistics network. The tunnel rail link is expected to:

  • Facilitate direct freight access to hinterland markets in Tamil Nadu, Karnataka, Andhra Pradesh, and Telangana
  • Reduce dependency on transhipment via Colombo
  • Support regional industries, including agriculture, fisheries, and manufacturing
  • Align with national infrastructure initiatives such as PM Gati Shakti and Sagarmala

Economic and Employment Impact

Government sources indicate that the project will generate substantial employment during both construction and operation phases. It is expected to:

  • Create thousands of direct and indirect jobs
  • Stimulate local economies through improved freight movement
  • Enhance state revenue through increased port utilisation

The Engineering, Procurement and Construction (EPC) tender for the proposed tunnel rail connectivity between Vizhinjam International Seaport and Balaramapuram railway station will be open to qualified entities with demonstrable expertise in large-scale infrastructure delivery. The tender is being issued by the Government of Kerala, in collaboration with Vizhinjam International Seaport Ltd (VISL) and Konkan Railway Corporation Ltd (KRCL), and will be published via the official e-Tender portal of the state government.

Eligibility Criteria

The following categories of applicants will be eligible to participate:

  • National and international infrastructure firms with a proven track record in executing complex rail and tunnelling projects, particularly those involving deep excavation and NATM (New Austrian Tunnelling Method) techniques.
  • Joint ventures and consortia, provided they collectively meet the prescribed technical and financial thresholds. Each member of the consortium must be legally registered and demonstrate relevant experience in their respective scope of work.
  • Companies registered under Indian law, including public and private limited companies, partnerships, and LLPs. Foreign entities may also apply, provided they operate through an Indian subsidiary or in partnership with a registered Indian firm.

Applicants must not be blacklisted or barred from participating in public procurement by any government agency in India or abroad.

Application Procedure

Interested bidders must undertake the following steps:

  1. Registration: All applicants must register on the Kerala Government’s e-Tender portal (https://etenders.kerala.gov.in) before the release of the tender. Registration includes obtaining a valid Digital Signature Certificate (DSC) and creating a bidder profile.
  2. Document Submission Bidders will be required to submit a comprehensive Pre-Qualification (PQ) dossier, which shall include:

Audited financial statements for the past three financial years

Details of completed and ongoing infrastructure projects, particularly those involving rail and tunnelling

Technical capacity statements, including equipment inventory and key personnel profiles

Legal documentation such as incorporation certificates, GST registration, and PAN details

  1. Compliance Requirements: All bidders must demonstrate compliance with:

NATM-specific engineering standards, including tunnel design, support systems, and excavation protocols

Environmental regulations, including impact mitigation, waste management, and groundwater protection

Safety and operational protocols, aligned with Indian Railways and international tunnelling norms

  1. Bid Submission and Evaluation: Once the tender is published, bidders must submit their technical and financial proposals within the stipulated deadline. The evaluation will be conducted in two stages:

Technical Evaluation: Based on project experience, engineering methodology, safety planning, and resource deployment

Financial Evaluation: Based on cost competitiveness, payment terms, and financial robustness

The Government of Kerala is expected to announce pre-bid meetings following the final review of tender documents in early September. These sessions will allow prospective bidders to seek clarifications, raise concerns, and understand the scope and expectations in greater detail. Responses to queries will be published as part of the tender addendum.

While the project has garnered wide-ranging support, officials acknowledged that land acquisition delays remain a persistent bottleneck. The government is reportedly working to streamline acquisition processes and ensure a timely rollout. Construction is expected to commence in 2026, with completion targeted by the end of 2028.

A senior government official stated that the tender process marks a pivotal step in repositioning Vizhinjam as a cargo gateway, with timely execution critical to unlocking regional growth. Industry observers have praised the initiative for its potential to model sustainable infrastructure and inclusive development.

This tender represents a landmark opportunity to contribute to one of India’s most ambitious port-linked infrastructure projects, where engineering excellence meets strategic vision.

FAQs

1. What is the scope of the Vizhinjam–Balaramapuram tunnel rail project?

The project involves the construction of a 10.7 km rail corridor, of which approximately 9.4 km will be developed as a deep tunnel using the New Austrian Tunnelling Method (NATM). It aims to establish direct freight connectivity between Vizhinjam International Seaport and Balaramapuram railway station, enhancing cargo movement across southern India.

2. Who is eligible to apply for the EPC tender?

The tender is open to:

  • National and international infrastructure firms with experience in large-scale rail and tunnelling projects
  • Joint ventures and consortia meeting the prescribed technical and financial criteria
  • Companies registered under Indian law, or foreign entities operating through an Indian partner or subsidiary

Applicants must not be blacklisted by any government agency and must demonstrate compliance with safety, environmental, and engineering standards.

3. How can interested bidders apply?

Eligible bidders must:

  • Register on the Kerala Government’s official e-Tender portal: https://etenders.kerala.gov.in
  • Obtain a valid Digital Signature Certificate (DSC)
  • Submit pre-qualification documents, including financial statements, project experience, technical capacity, and legal credentials
  • Upload technical and financial bids within the stipulated deadline once the tender is published

4. What are the key compliance requirements for bidders?

Bidders must adhere to:

  • NATM-specific engineering protocols for tunnel construction
  • Environmental regulations, including groundwater protection and waste management
  • Safety standards aligned with Indian Railways and international tunnelling norms

5. Will there be a pre-bid meeting or clarification session?

Yes. The Government of Kerala is expected to announce pre-bid meetings following the final review of tender documents in early September. These sessions will allow bidders to seek clarifications and better understand project expectations. Responses will be published as part of the tender addendum.

6. What is the expected timeline for the project?

  • Tender publication: September 2025
  • Bid submission deadline: To be specified in the tender notice
  • Contract award: Expected by Q1 2026
  • Construction commencement: Mid-2026
  • Project completion: Targeted by the end of 2028

7. What is the strategic significance of this project?

The tunnel rail link is expected to:

  • Improve freight access to hinterland markets in Tamil Nadu, Karnataka, Andhra Pradesh, and Telangana
  • Reduce dependency on transhipment via Colombo
  • Support regional industries and stimulate economic growth
  • Align with national infrastructure initiatives such as PM Gati Shakti and Sagarmala